European Union laws set a 42-working-day default for defence project permits, capped at 102 working days with tacit approval, entering into force 20 days after Official Journal publication.
The European Parliament and the Council of the EU have moved three defence simplification laws to final adoption, setting time limits on permits for defence factories, easing cross-border transfers of defence products and loosening defence procurement rules from 20 days after publication in the EU’s Official Journal1.
The package belongs to the "Omnibus V" simplification measures, which Parliament approved on Sept. 16, 20261. The Council’s ambassadors placed all three acts on their Sept. 30 agenda for "adoption of the legislative act"2.
In short, national authorities will have a fixed clock to decide on permits for defence plants, and silence past the deadline will count as approval. Defence makers, their suppliers and the governments that buy from them will face fewer licences and lighter procurement steps.
Which three EU defence laws are involved?
The Council agenda lists the three acts by name2:
- a regulation on faster permit-granting for defence readiness projects
- a regulation on defence readiness and easier defence investment
- a directive simplifying intra-EU transfers and security and defence procurement
The directive amends two existing laws, Directive 2009/43/EC on transfers and Directive 2009/81/EC on defence procurement3. A directive sets goals that each EU country must write into its own law. A regulation applies directly.
Parliament said the package aims to support up to €800 billion in defence investment over the next four years1. The directive links that figure to projections of gradual take-up, including €150 billion from the SAFE loan instrument3.
How does the Council adopt the permit regulation?
The Council’s general secretariat asked ambassadors to recommend that ministers approve Parliament’s position, as set out in document PE-CONS 44/264. It proposed this as an "A" item, a point adopted without debate, with Austria abstaining4.
Path of the permit regulation
Once the Council approves Parliament’s position, the act is adopted4. The presidents of Parliament and the Council then sign it, and it is published in the Official Journal4. The rules enter into force on the 20th day after that publication1.
The Commission first proposed the permit regulation on June 17, 20254. Negotiators from Parliament and the Council reached an informal deal on June 10, 20261.
What are the new defence permit deadlines?
The permit rules cover defence projects such as building new factories or expanding existing sites1. National authorities must decide within a default period of 42 working days from confirming that an application is complete1.
Defence permit decision limits, working days
In exceptional cases, authorities may extend the deadline at most twice, by up to 60 days1. Examples include complex projects or risks to the environment or to worker health and safety1. Even then, the whole process may not exceed 102 working days1.
Any extension must be sent to the project promoter with a reason and an expected decision date1. Parliament’s vote on this text was 540 in favour, 105 against and 22 abstentions1.
What happens if a permit authority misses the deadline?
If an authority does not act by the deadline, tacit approval applies1. Tacit approval means the permit counts as granted because the authority stayed silent.
The authority should then inform the promoter within 8 working days of the deadline passing1. It must state the requirements the permit is subject to1.
Each EU country must also set up a single point of contact for defence project promoters1. These offices will track applications digitally, report yearly to the Commission on permit activity and support small and medium-sized firms (SMEs)1. The EU will monitor tacit approvals to keep practice consistent1.
How do defence transfer licences change?
Moving defence products between EU countries needs prior authorisation through general, global or individual transfer licences3. A general transfer licence is a published permission that any eligible supplier can use without applying one by one.
Main changes to intra-EU defence transfers
| Dimension | Provision |
|---|---|
| New general licences | Between certified suppliers and certified recipients |
| EU-funded projects | General licences for EU defence industrial programmes, such as the European Defence Fund |
| Publication | Member states must publish the licences |
| Wider exemptions | PESCO projects, industrial partnerships, EU bodies, crisis transfers |
| Commission power | May add exempt cases through delegated acts |
The directive creates new general transfer licences, including one for transfers between certified suppliers and certified recipients3. It also requires licences for projects funded by EU defence industrial programmes, such as the European Defence Fund3. Member states must publish these licences, giving industry a more predictable framework1.
Countries may also exempt more transfers from prior authorisation3. The cases include joint projects under Permanent Structured Cooperation (PESCO), structured industrial partnerships, transfers to EU bodies and the European Defence Agency, and urgent transfers in a crisis3. The Commission gains power to add new exempt cases through delegated acts, rules it adopts under powers granted by the law3.
What changes in defence procurement?
The directive raises the contract value thresholds above which EU defence procurement rules apply3. Smaller contracts below the thresholds still follow general principles such as transparency and equal treatment3.
Framework agreements, long-term deals setting terms for future orders, may now run up to 10 years, up from seven1. Member states also gain more freedom to run occasional joint purchases1.
Buyers gain two procedures from the general procurement rules: the open procedure and the dynamic purchasing system, an electronic process for repeat purchases3. A more flexible innovation partnership procedure is added to support buying research and new technology3. Parliament approved this text by 549 votes to 92, with 27 abstentions1.
What else does the defence readiness regulation do?
The third law simplifies how the European Defence Fund (EDF) is run and updates the award criteria projects must meet1. It raises support for activities involving SMEs and extends higher funding to actions under a Structure for European Armament Programme1. Costs of testing in Ukraine become eligible for EDF funding1.
EU countries may also apply certain exemptions from EU environmental and chemical rules in the interest of defence, when justified1. Parliament backed this text by 530 votes to 125, with 12 abstentions1.
Summary of the EU defence readiness simplification package
The table sets out the main points of the three laws.
| Key Dimension | Details |
|---|---|
| Regulating Authority & Jurisdiction | European Parliament and Council of the EU; applies across all EU member states1 |
| Scope & Who Must Comply | National permit authorities, defence makers and suppliers, and defence procurement bodies1 |
| Core Mandate / Key Change | Fixed permit deadlines with tacit approval, new general transfer licences, simpler procurement1 |
| Permit Time Limits | 42 working days by default; maximum 102 working days with extensions1 |
| Procurement Thresholds | Higher contract value thresholds; framework agreements up to 10 years instead of seven1 |
| Transfer Licences | New general licences, including between certified suppliers and recipients and for EU-funded projects3 |
| Key Dates & Implementation Milestones | Parliament vote Sept. 16, 2026; adoption listed on Council ambassadors’ Sept. 30 agenda2; in force 20 days after publication |
| Enforcement / Oversight | Tacit approval if authorities miss deadlines; yearly reporting to the Commission; EU monitoring1 |
The next milestone is signature by the two presidents and publication in the Official Journal4. The laws enter into force 20 days after that publication1.
Sources
- ↩ Parliament backs new measures to strengthen Europe’s defence readiness | News | European Parliament https://www.europarl.europa.eu/news/en/press-room/20260911IPR47458/parliament-backs-new-measures-to-strengthen-europe-s-defence-readiness
- ↩ pdf — en / pdf https://data.consilium.europa.eu/doc/document/ST-13440-2026-INIT/en/pdf
- ↩ pdf — en / pdf https://data.consilium.europa.eu/doc/document/PE-46-2026-INIT/en/pdf
- ↩ pdf — en / pdf https://data.consilium.europa.eu/doc/document/ST-13479-2026-REV-1/en/pdf